- July 2003, the design project officially settled.
-
-
December 24, 2003, earthworks started. -
-
May 2005, the main concrete structure completed. -
-
June 2005, the steel structure to be installed. -
-
April 10, 2006, the main structure topped off, and its steel structure installed. -
-
June 16, 2006, the supportive structures removed. -
-
August 1, 2006, the first air cushion installed. -
-
December 26, 2006, the membrane structures installed outside. -
-
January 2007, the decoration and fit-up process started. -
-
March 2007, the municipal engineering works beginning. -
-
September 2007, the electro-mechanical equipment installed. -
-
January 28, 2008, the venue inaugurated and delivered for use